Status as of November 26, 2026
- Test and training location
- Vandenberg Space Force Base, California
- Inert test article assembly
- Announced September 14, 2026
- First flight test target
- 2027
- Initial capability target
- Early 2030s
A new program at an established test base
Vandenberg Space Force Base already supported the Minuteman III test program when the Air Force began preparing it for Sentinel. The California installation also became a site for training and support construction for the new program. The Air Force assigned Sentinel Task Force Detachment 9 to help coordinate preparations there. [1] [2] [4]
The Air Force reported completing ground qualification tests in 2025 as it prepared for flight testing. On September 14, 2026, it announced that it had assembled an inert Sentinel test article at Vandenberg and completed the design review for its first flight test. The Air Force was targeting that flight for 2027. [3] [6]
Building a school for operators and maintainers
Military and civilian partners broke ground for the Sentinel Formal Training Unit on August 17, 2026. The Air Education and Training Command project brings initial training for missile operators and technical instruction for maintainers onto one campus. The Air Force expects the facility to be completed in the early 2030s. [4]
Preparing instructors and students is a separate part of the transition from building and testing the missile. The school will prepare personnel for assignments with Sentinel as the missile wings move to the new system. The groundbreaking marked the start of construction for that training mission. [4]

The first completed Sentinel construction at Vandenberg
On November 5, 2026, Sentinel Task Force Detachment 9 marked completion of the Sentinel Stage Processing Facility with a ribbon-cutting ceremony. Space Launch Delta 30 called it Vandenberg's first completed military construction project for Sentinel. The facility supports the preparation of test articles for flight testing. [5]
The path from test to service
The Air Force's February 2026 plan called for completing the restructure and seeking renewed development approval by the end of 2026. It targeted the early 2030s for initial capability. In July, the Government Accountability Office reported continuing uncertainty about the program's revised costs and schedule. [6] [7]
The 2027 flight-test target belongs to Sentinel's development program. Fielding requires its own approvals, infrastructure and training, and the changeover will be phased across the missile wings. The Air Force is sustaining Minuteman III during that work. [3] [6] [8]
Chronology
- 2025 - Sentinel completes ground qualification tests ahead of flight testing. [6]
- February 17, 2026 - The Air Force announces revised targets for development approval and initial capability. [6]
- August 17, 2026 - Partners break ground for the Sentinel Formal Training Unit at Vandenberg. [4]
- September 14, 2026 - The Air Force announces inert test article assembly at Vandenberg and identifies 2027 as its flight-test target. [3]
- November 5, 2026 - The task force marks completion of Vandenberg's first Sentinel military construction project. [5]
Related sites
Information sources (8)
- WEBU.S. Space Force, Minuteman III Vandenberg test announcement, February 2025
Documents Vandenberg's established role in Minuteman III operational testing.
- WEBAir Force Global Strike Command, LGM-35A Sentinel fact sheet
Program context and the planned transition from Minuteman III.
- WEBU.S. Air Force, inert Sentinel assembly announcement, September 2026
Assembly at Vandenberg, first-flight design review and the announced 2027 test target.
- WEBSpace Launch Delta 30, Sentinel Formal Training Unit groundbreaking, August 2026
Groundbreaking, training roles and Air Force construction target.
- WEBSpace Launch Delta 30, Sentinel facility ribbon cutting, November 2026
First completed Sentinel military construction project at Vandenberg and November 5 ceremony.
- WEBU.S. Air Force, Sentinel restructuring and initial capability announcement, February 2026
Ground qualification milestones and revised development approval and initial capability targets.
- PDFGovernment Accountability Office, Weapon Systems Annual Assessment, July 2026
Uncertainty about Sentinel's revised cost and schedule. See pages 91-92.
- WEBGovernment Accountability Office, ICBM Modernization, September 2025
Minuteman III sustainment and phased transition oversight.